Kostolac Wind Farm

20

Wind Turbine Generators

Our team handled customs clearance in Constanta, ensuring all necessary documentation was completed efficiently.

 

We oversaw port operations in Constanta, including the temporary storage of wind turbine components to fit the logistics schedule.

​

The transportation of these components was carried out using barge transport from Constanta to Kostolac. Each piece was securely fastened and transported without any issues.

 

​

Photopea (1).png
man truck TGX nacelle transport constanta port (1) (1).png
port operatiosn kostolac wind facm Constanta (1) (1) (1).png

Throughout the project, our careful planning and execution ensured that all wind turbine components were handled with the utmost care and efficiency.

The Kostolac onshore wind farm consists of 20 Siemens Gamesa wind turbines SG 3.3-132 turbines, each with a nameplate capacity of 3.65 MW.

 

This farm is expected to meet the annual power needs of approximately 30,000 households, producing around 187 gigawatt-hours (GWh) of electricity each year.

 

This production will replace about 95,000 tons of coal needed for the same power demand.

Construction began in 2022, and the farm is set to enter commercial operation by 2025. 